1 1 vote A contractor agreed to construct a $6 \; \text{km}$ road in $200 \; \text{days}.$ He employed $140$ persons for the work. After $60 \; \text{days},$ he realized that only $1.5 \; \text{km}$ road has been completed. How many additional people would he need to employ in order to finish the work exactly on time $?$ Quantitative Aptitude cat2020-set3 quantitative-aptitude work-time numerical-answer + – soujanyareddy13 2.8k points 2.0k views answer comment Share Follow Print 0 reply Please log in or register to add a comment.
1 1 vote Let the additional people need be $x.$ If $M_{1}$ person can do $W_{1}$ work in $D_{1}$ days working $T_{1}$ hours in a day and $M_{2}$ person can do $W_{2}$ work in $D_{2}$ days working $T_{2}$ hours in a day then the relationship between them is : $$ \boxed {\frac{M_{1} \ast D_{1} \ast T_{1}}{W_{1}} = \frac{M_{2} \ast D_{2} \ast T_{2}}{W_{2}}} $$ Now, $ \dfrac{140 \times 60}{1.5} = \dfrac{(x+140) \times 140}{4.5} $ $ \Rightarrow 180 = x + 140 $ $ \Rightarrow x = 180 – 140 $ $ \Rightarrow \boxed{x = 40} $ $\therefore$ The number of additional people needed is $40.$ Correct Answer$: 40$ Anjana5051 answered Oct 31, 2021 • edited Nov 1, 2021 by Lakshman Bhaiya Anjana5051 12.1k points comment Share Follow 0 reply Please log in or register to add a comment.