There are six companies, $1$ through $6.$ All of these companies use six operations, A through F. The following graph shows the distribution of efforts put in by each company in these six operations.

Suppose effort allocation is interchanged between operation B and C, then C and D, and then D and E. If companies are then ranked in ascending order of effort in E, what will be the rank of company 3?

  1. $2$
  2. $3$
  3. $4$
  4. $5$

Please log in or register to answer this question.

Position:
Show:

Related questions

0 0 votes
0 0 answers
1.5k
1.5k views
go_editor asked Apr 24, 2016
1,478 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
0 0 answers
1.5k
1.5k views
go_editor asked Apr 24, 2016
1,534 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
0 0 answers
1.4k
1.4k views
go_editor asked Apr 24, 2016
1,430 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
0 0 answers
1.2k
1.2k views
go_editor asked Apr 24, 2016
1,238 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
1 1 answer
1.7k
1.7k views
go_editor asked Apr 24, 2016
1,725 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...