Recent questions tagged project-planning-and-network-analysis
0
votes
0
answers
1
GATE Civil 2024 Set 1 | Question: 6
Consider the statements $\text{P}$ and $\text{Q}$. $\text{P}$: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase. $\text{Q}$: Client's Detailed Estimate is used for controlling costs during the execution ... Both $\mathrm{P}$ and $\mathrm{Q}$ are FALSE $\mathrm{P}$ is FALSE and $\mathrm{Q}$ is TRUE
Consider the statements $\text{P}$ and $\text{Q}$.$\text{P}$: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.$\text...
admin
4.2k
points
admin
asked
Feb 16
Others
gatecivil-2024-set1
project-planning-and-network-analysis
+
–
0
votes
0
answers
2
GATE2016-2-10
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below. ... $11-12$ for the project are, respectively, $25$ and $1$ $1$ nd $1$ $0$ and $0$ $81$ and $0$
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network di...
Milicevic3306
11.9k
points
Milicevic3306
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-2
construction-materials-and-management
structural-engineering
project-planning-and-network-analysis
cost-estimation
+
–
0
votes
0
answers
3
GATE2016-2-39
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below in arrows. The critical duration for this construction project is $13$ days $14$ days $15$ days $16$ days
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below in ...
Milicevic3306
11.9k
points
Milicevic3306
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-2
construction-materials-and-management
structural-engineering
project-planning-and-network-analysis
+
–
0
votes
0
answers
4
GATE2016-1-39
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O – M – P. The expected completion time (in days) of the project is ________
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O – M – P.The ex...
Milicevic3306
11.9k
points
Milicevic3306
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-1
numerical-answers
structural-engineering
construction-materials-and-management
project-planning-and-network-analysis
+
–
To see more, click for the
full list of questions