Consider the following data for a project of $300$ days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. $200$
Budgeted Cost of Work Performed (BCWP) = Rs. $150$
Actual Cost of Work Performed (ACWP) = Rs. $190$
The 'schedule variance' for the project is
- (-)Rs. $50$
- (-)$50$ days
- (+)Rs. $50$
- (+)$50$ days