$A$ can complete half work in $7$ days $B$ can do $\dfrac{1}{3}$ of work in $14$ days .while $C$ can complete the $20\%$ of the remaining work in $\dfrac{28}{5}$ days. In how many days $A,B,C$ will complete the work together ?
edited by

3 Answers

4 votes
4 votes
$A$ does $\dfrac{1}{2}^{th}$ work in $7$ days

So, in $\dfrac{7}{\dfrac{1}{2}} = 7 \times 2 = 14 $ days $A$ can complete the whole work

$B$ does $\dfrac{1}{3}^{th}$ work in $14$ days

So, in  $\dfrac{14}{\dfrac{1}{3}} = 14 \times 3 = 42 $ days $B$ can complete the whole work

Now, remaining work = $\left ( 1 - \dfrac{1}{2} + \dfrac{1}{3} \right ) = \left ( 1 - \dfrac{5}{6} \right ) = \dfrac{6 - 5}{6} = \dfrac{1}{6}$

& $20\%$ of the remaining work = $\dfrac{1}{6} \times 20\% =\dfrac{1}{6} \times \dfrac{1}{5} =\dfrac{1}{30}$

∴ $C$ does $\dfrac{1}{30}^{th}$ work in $\dfrac{28}{5}$ days

So, in $\dfrac{\dfrac{28}{5}}{\dfrac{1}{30}} = \dfrac{28}{5} \times 30 = 28 \times 6 = 168$ days $C$ can complete the whole work

Now, LCM of $(14, 42, 168) = 168$

∴ Total units of work = $168 $ units

∴ $A$ can complete $\dfrac{168}{14} = 12$ units of work in $1$ day

$B$ can complete $\dfrac{168}{42} = 4$ units of work in $1$ day

$C$ can complete $\dfrac{168}{168} = 1$ units of work in $1$ day

When $A, B, C$ works together in $1$ day total work done = $12+4+1 = 17$ units

∴ To complete $168$ units $A, B, C $ have to work for $\dfrac{168}{17} = 9.88$ days

∴ To complete the whole work $A, B, C$ have to work together for $9.88$ days.
edited by
1 votes
1 votes
$A$ can complete half work in $7$ days. So, speed of work of $A = \frac{x}{2\times 7} = \frac{x}{14}$ where $x$ is the amount of work to be done.

Similarly speed of work of $B = \frac{x}{42}$

Given that $A$ is doing half the work and $B$ is doing $1/3$ the work. So, remaining work $= 1 - 1/2 - 1/3 = 1/6.$ $C$ can complete $20\%$ of this in $28/5$ days. So,

speed of work of $C = \frac{0.2 \times 5x}{28 \times 6} = \frac{x}{168}$

Now, when $A, B$ and $C$ work together, their combined speed will be$ = \frac{x}{14} + \frac{x}{42} + \frac{x}{168} = \dfrac{12x+4x+x}{168} = \dfrac{17x}{168} $

So, amount of time required $=\dfrac{x}{\frac{17x}{168}} = \dfrac{168}{17}$

Related questions

0 votes
0 votes
2 answers
1
Lakshman Bhaiya asked Mar 31, 2020
1,364 views
Ali is thrice as good as workman as Birju and therefore is able to finish a job in $60$ days less than Birju. If both Ali and Birju, work together, they can do it in:$20$...
0 votes
0 votes
1 answer
2
Abhipsa asked Mar 26, 2020
1,393 views
Some part of a sugar solution which contains 40% sugar is replaced with another sugar solution which contains 19% sugar. Part of sugar in the new mixture became 26% what ...
0 votes
0 votes
1 answer
3
iarnav asked Jan 28, 2018
3,579 views
How many four-digit numbers, with distinct digits are there such that the sum of the digits of each of these numbers is an odd natural number?$2160$$2090$ $1880$ $2376$
1 votes
1 votes
2 answers
4
Shubham Aggarwal asked Nov 13, 2018
1,047 views
In a Conventional Clock, how many times does the minutes hand pass the hour hand between noon and midnight?
0 votes
0 votes
1 answer
5
xxwarmachineroxx asked Nov 4, 2023
611 views
A container has 20 L of milk. 4 L of milk is replaced with an equal quantity of water. What was will be the final quantity of milk in the container if the process is repe...